Urbane Construction Update #2

Urbane Canberra,

Welcome to the second Urbane construction update. Find your block below to see its current status.

Block 1

  • Frames and trusses erected
  • Windows installed
  • Brickwork nearing completion
  • Electrical and hydraulic rough ins commenced
  • Roofing commencing mid-September 2017

Block 2

  • Frames and trusses erected
  • Windows installed
  • Brickwork nearing completion
  • Electrical and hydraulic rough ins commenced
  • Roofing commencing mid-September 2017

Block 3

  • Frames, trusses, windows and roofing installed
  • Electrical, hydraulic and mechanical rough ins complete
  • Plasterboard commencing

Block 4

  • Frames, trusses, windows and roofing installed
  • Electrical, hydraulic and mechanical rough ins complete
  • Plasterboard commencing

Block 5

  • Plasterboard and painting commenced
  • Ceramic tiling due to commence
  • Joinery commenced

Block 6

  • Plasterboard completed
  • Carpentry fix underway
  • Some joinery installed
  • Ceramic tiling commenced
  • Painting commenced

Block 7

  • Plasterboard and carpentry fix completed
  • Joinery, painting and ceramic tiling nearing completion
  • External scaffolding removed

Block 8

  • Frames, trusses and windows installed
  • External scaffold erected
  • Electrical hydraulic rough ins commenced
  • Roofing to commence mid to late September 2017

During construction of your new property, Peter Blackshaw Real Estate will keep you up to date with progress, important information and photos of construction milestones.

We hope that you’re getting excited, seeing your beautiful new property come to life. If you have any questions, please feel free to contact us.