Urbane Construction Update #1

Urbane Canberra,

Welcome to the first Urbane construction update. Find your block below to see its current status.

Block 1

  • In-ground electrical and hydraulics installed
  • Concrete slabs due to be poured on June 13th

Block 2

  • In-ground electrical & hydraulics installed
  • Concrete slabs due to be poured on June 13th

Block 3

  • Concrete slabs poured
  • Wall frames, flooring and windows installed up to the first-floor level

Block 4

  • Concrete slabs poured
  • Wall frames, flooring and windows installed up to the first-floor level

Block 5

  • Concrete slabs poured
  • Wall frames, flooring and windows installed up to the first-floor level

Block 6

  • Concrete slabs poured
  • Ground and first floor timber wall frames and windows installed
  • Brickwork is installed up to first floor level, scaffold and roof trusses have been commenced

Block 7

  • Concrete slabs poured
  • Ground and first floor frames and windows installed
  • Brickwork is installed up to first floor level, scaffold and roof trusses have been commenced
  • Hydraulics and electrical works have commenced

Block 8

  • In-ground electrical and hydraulics installed

During construction of your new property, Peter Blackshaw Real Estate will keep you up to date with progress, important information and photos of construction milestones.

We hope that you’re getting excited, seeing your beautiful new property come to life. If you have any questions, please feel free to contact us.