Urbane Construction Update #1
Welcome to the first Urbane construction update. Find your block below to see its current status.
Block 1
- In-ground electrical and hydraulics installed
- Concrete slabs due to be poured on June 13th
Block 2
- In-ground electrical & hydraulics installed
- Concrete slabs due to be poured on June 13th
Block 3
- Concrete slabs poured
- Wall frames, flooring and windows installed up to the first-floor level
Block 4
- Concrete slabs poured
- Wall frames, flooring and windows installed up to the first-floor level
Block 5
- Concrete slabs poured
- Wall frames, flooring and windows installed up to the first-floor level
Block 6
- Concrete slabs poured
- Ground and first floor timber wall frames and windows installed
- Brickwork is installed up to first floor level, scaffold and roof trusses have been commenced
Block 7
- Concrete slabs poured
- Ground and first floor frames and windows installed
- Brickwork is installed up to first floor level, scaffold and roof trusses have been commenced
- Hydraulics and electrical works have commenced
Block 8
- In-ground electrical and hydraulics installed
During construction of your new property, Peter Blackshaw Real Estate will keep you up to date with progress, important information and photos of construction milestones.